roadHouse of Representatives and House of Peoples of the FB&H approved a decision on accepting the debit of the FB&H according to the Loan Agreement of B&H and the OPEC Fund for International Development (OFID) for realization of the project Corridor 5-C in the amount of 24 million EUR and 48 million USD.

This way, the funds for further construction of the section Zenica South – Zenica North, more specifically for subsection Donja Gracanica – Klopce were provided, as confirmed from the PE Highways of FB&H.

“This subsection is passing through very demanding terrain, with great altitudes at short distances, and even at a distance of about 6 kilometers, and 4 viaducts and 2 tunnels are planned by project,” as emphasized from the PE Highways of FB&H, adding that they received permissions for construction.