On Wednesday at 10 p.m., Unit 4 was suspended, and Unit 3 with one boiler was put into operation as a replacement capacity. These are plants in which thermal energy is produced for heating about 120 thousand citizens of Tuzla and Lukavac.
“Unit 3 will be in operation with both boilers in the next weekwhen colder weather is forecasted. The necessary quantities of coal for its operation will be provided from the Banovici and Stanari mines.”
”Next week, the production of electricity and technological steam for the industry will be performed only on Unit 6, whose work is more difficult and is currently based on flow reception, which means that all delivered quantities of coal are immediately transported to the production process,” it was said by the EPBiH.
“Thermal Power Plant Tuzla informed the users of thermal energy and technological steam about a possible reduction in supply caused by the suspension of coal deliveries from the Concern’s mines. Due to the difficult operation of the plant in Tuzla, all three units and their further functioning arequestionable from the technological and security aspects. “
”To recall, production in the Zenica, Breza, and Kakanj mines, as announced during the miners ‘protest in Sarajevo, was suspended due to workers’ disobedience of the miners of seven mines of the EPBiH Concern. Production has been suspended and will remain so until our requirements are met, ” stated Abdel Fazlic, president of the Kakanj black coal mine Workers’ Union.
E.Dz.
Source: BHRT