Workers began to set up the wooden beams for the new structure of the roof by the end of February and so far almost 75 % of the work has been done, said Voljevica.
The new roof structure is finalized on the part of Alipašina Mosque and Koševo stream, and currently is working on the roof on interior side. According to the schedule of works, the complete roof structure should be set up by the end of this week.
In addition, workers continue to remove mortar from the very burnt and damaged walls. After having finished the scraping of mortar along the very damaged staircase, this is currently being done in the basement premises where the burned-out electrical cables and mechanical installations are being set-up, said Voljevica.
The fixing of electric and other equipment that are partially damaged is ongoing. Also, there are works on additional security and fire protection server rooms.
(Source: Fena)