Reading: Construction of Hranjen Tunnnel is progressing according to the planned Dynamics (video)
Share
Font ResizerAa
Sarajevo TimesSarajevo Times
Font ResizerAa
  • HOME
  • POLITICS
  • BUSINESS
  • BH TOURISM
  • INTERVIEWS
  • SPORT
  • ARTS
  • W&N
Search
  • HOME
  • POLITICS
    • BH & EU
  • BUSINESS
  • BH TOURISM
  • INTERVIEWS
    • BH & EU
    • BUSINESS
    • ARTS
  • SPORT
  • ARTS
    • CULTURE
    • ENTERTAINMENT
  • W&N
Follow US
  • ABOUT US
  • IMPRESSUM
  • NEWSLETTER
  • CONTACT
© 2012 Sarajevo Times. All rights reserved.
Sarajevo Times > Blog > BUSINESS > Construction of Hranjen Tunnnel is progressing according to the planned Dynamics (video)
BUSINESS

Construction of Hranjen Tunnnel is progressing according to the planned Dynamics (video)

Published: January 31, 2020
Share
SHARE

 

The construction of the Hranjen tunnel on the route of the future highway Gorazde-Sarajevo, regardless of weather conditions, is progressing according to the planned dynamics.

The tunneling is done at the same time from the north and south, from the direction of Gorazde and Praca. The investor is Public Enterprise Motorways of FBiH, and the works entrusted to Euro-Asfalt are worth around 82 million BAM.

Euro-Asphalt says that it is a geologically demanding terrain, but for now there are no special problems. The southern portal of the tunnel from the direction of Gorazde is slowly but surely progressing towards the northern portal near Hrenovica, about five kilometers away, eKapija reports.

“At the moment, we are in the main tube for about 310 meters. Works are progressing according to planned dynamics. Extremely cold weather, which in the last three to four weeks has created a lot of difficulties, but all precautions were taken to protect people and mechanization, so there were no major problems and the works were carried out according to the planned dynamics,” explains the technical manager on the tunnel Enes Ajanovic.

On March 4ththis year, the Government of Bosnian-Podrinje Canton Gorazde in cooperation with Public Enterprise “Autoceste” of the Federation, will solemnly intensify the start of works on the construction of the tunnel Hranjen today, as part of the realization of the project for the construction of the fast road Gorazde-Sarajevo.

In the Municipality of Pale in the Federation of Bosnia and Herzegovina, preparatory works for breaking the tunnel “Hranjen” are underway, as part of a future fast road connecting Gorazde with Sarajevo.

The Prime Minister of Bosnia Podrinje Canton (BPK) Gorazde Emir Okovic, who together with the Mayor of Pale visited the site, pointed out that in spite of the bad weather conditions, the construction of the necessary infrastructure is proceeding with the planned dynamics, and in accordance with the contract concluded with the contractor, Federal News Agency reports.

At the moment, construction of the access road is in progress and according to Okovic, extensive preparatory works include the installation of a concrete base and other preparations for construction.

“We are encouraged by the fact that, in spite of the weather conditions, the contractor did not stop and does what is possible in order to reach the main works in the foreseen term, that is, to the excavation of the tunnel portal itself. Concrete works can be expected with the improvement of weather conditions, that is, in the early spring. Until then, it is necessary to provide all infrastructure, make access roads through the Praca River and to the entrance to the portal,” said Okovic.

He added that BPK Goražde issued the required consents.

“The total value of the construction of the tunnel amounts to 190 million BAM and the planned deadline for its construction is 36 months. The announced tender refers to the first phase of the construction, i.e. the breakthrough of the tunnel and installation of the supporting facilities, which represents the most important and demanding part of the construction of this type of object. The cost of the construction in the first phase of works amounts to a total of 70 million BAM.”

Specificity of this tunnel is that it will have two tubes, despite containing two lanes for the traffic.

The construction of the tunnel “Hranjen” represents a historic project for Gorazde, because the distance will be decreased from the current 95.6 kilometers to 56 kilometers.

After the construction of tunnel Hranjen, and given the quality of the new route, the ride between Sarajevo and Gorazde will last for 45 minutes instead of the hour and a half.

In the video below, you can see how the Tunnel Hranjen will look like:

Faruk Smajevic: CIO Oscar is the most Important IT event in BiH this Year
IGC: Together we can stop the Crime of Holocaust and Genocide Denial
1,200 People are employed every Month in BiH?
Federation of BiH declares the First Non-Working Sunday
Decrease in Prices for about 80 Medicines in RS starting Today
TAGGED:#BiH#Gorazde#highway#hranjen#sarajevo#tunnel
Share This Article
Facebook Whatsapp Whatsapp Telegram Threads Bluesky Email Print
Share
What do you think?
Love0
Sad0
Happy0
Sleepy0
Angry0
Dead0
Wink0
Previous Article Decrease in Number of Fixed Telephone Lines, SMS Messages Last Year
Next Article EUFOR Patrol provided Roadside Assistance to Two Cars in One Day in Tuzla
Leave a Comment Leave a Comment

Leave a Reply Cancel reply

You must be logged in to post a comment.

Stay Connected

10.2kFollowersLike
10.1kFollowersFollow
414FollowersFollow

Latest News

EUFOR Supported the 3rd International Coffee and Chocolate Fair in Tuzla
May 18, 2026
More than 30 Council of Europe Parliamentarians arrive in Sarajevo
May 17, 2026
The Museum of Literature and Theater Arts of BiH implements a Digital Library Project
May 17, 2026
New Law Makes Stay of Workers from BiH in Croatia Easier
May 17, 2026
34 Years Ago, Defenders of Sarajevo Thwarted Aggressors’ Hellish Plan
May 17, 2026
Academic Freedoms at Universities in BiH increasingly threatened by Political Pressures
May 17, 2026
BiH and Moldova Move Toward First-Ever Scheduled Air Links
May 17, 2026
SOC: LGBTI Persons in BiH still without full Protection
May 17, 2026
Three Gold and One Silver Medal for Young BiH Athletes
May 17, 2026
Schmidt Signals Possible Breakthrough on State Property Issue in BiH
May 17, 2026
Sarajevo TimesSarajevo Times
Follow US
© 2012 Sarajevo Times. All Rights Reserved.
  • ABOUT US
  • IMPRESSUM
  • NEWSLETTER
  • CONTACT
Go to mobile version
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?