By using this site, you agree to the Privacy Policy and Terms of Use.
Accept
Sarajevo TimesSarajevo TimesSarajevo Times
  • HOME
  • POLITICS
    • BH & EU
  • BUSINESS
  • BH TOURISM
  • INTERVIEWS
    • BH & EU
    • BUSINESS
    • ARTS
  • SPORT
  • ARTS
    • CULTURE
    • ENTERTAINMENT
  • W&N
Search
  • ABOUT US
  • IMPRESSUM
  • NEWSLETTER
  • CONTACT
© 2022 Foxiz News Network. Ruby Design Company. All Rights Reserved.
Reading: The Corridor Vc Saga – From Nothing to Nowhere
Share
Font ResizerAa
Sarajevo TimesSarajevo Times
Font ResizerAa
  • HOME
  • POLITICS
  • BUSINESS
  • BH TOURISM
  • INTERVIEWS
  • SPORT
  • ARTS
  • W&N
Search
  • HOME
  • POLITICS
    • BH & EU
  • BUSINESS
  • BH TOURISM
  • INTERVIEWS
    • BH & EU
    • BUSINESS
    • ARTS
  • SPORT
  • ARTS
    • CULTURE
    • ENTERTAINMENT
  • W&N
Follow US
  • ABOUT US
  • IMPRESSUM
  • NEWSLETTER
  • CONTACT
© 2012 Sarajevo Times. All rights reserved.
Sarajevo Times > Blog > BUSINESS > The Corridor Vc Saga – From Nothing to Nowhere
BUSINESS

The Corridor Vc Saga – From Nothing to Nowhere

Published: October 1, 2026
Share
SHARE

Absurdity in the corridor called longing, officially Corridor Vc. From the meadow, finally the entrance to the tunnel, and the exit from it again – to nothing! How did 400 square meters block around 600 million marks?! Namely, nearly 280 million marks are being invested in the Kvanj-Buna tunnel section, but there is no continuation towards Mostar. The next section Mostar south – the Kvanj tunnel, worth another 300 million, has been blocked for years, while penalties are coming for approved but not withdrawn money.

“It is the fastest excavated tunnel on Corridor Vc. It has a total length of 2.6 kilometers. Both pipes were excavated and broken through in less than a year,” said Asmir Dževlan, executive director of JP Autocesta for design and construction.

But the record is in vain if there is no continuation. Buna – Počitelj, a section that has ended in a meadow for years, now continues through Kvanj. And as soon as you get out of the tunnel – the wall again. The construction of the next section towards Mostar, 9.2 kilometers long and worth more than 300 million marks, has not even started. The money is secured as early as 2019. There is no work, but the bill is coming.

“Currently, 1.5 million marks have been paid as a penalty for the section Mostar south – Tunnel Kvanj. This is a contractual clause of the EBRD. That money is actually standing and waiting for us”, adds Dževlan.

The reason is 400 square meters. The route touches the “Miralem Jugo” barracks and the Ortiješ military airport. The BiH Presidency did not give its consent.

“Considering that the route of the highway, which finally passes through the Ortiješ airport, which is a prospective military location, i.e. state property, has been changed several times, and that the High Representative’s decision prohibits the disposal of state property, we cannot and do not want to violate the same decision,” said Željko Komšić.

In Autoceste, they argue, the military perspective of the location and the issue of state property are mixed up. From the Presidency, they say, they are not asking for a transfer of ownership or a permit to build on state land, but a decision – whether that location is still a military perspective.

“The Presidency does not give consent to build over state property. It needs to make a decision and say whether it agrees or disagrees with the question of whether it is a military perspective. And in other procedures it will be determined – as it has been determined so far on Corridor Vc – obtaining a decision on expropriation and entering the property in regular procedures,” emphasizes Dževlan.

Former BiH Ombudsman Ismet Velić warns that legal shortcuts and creative interpretations of regulations lead nowhere. The key question is whether there is still a real military need for that land. If it doesn’t exist, the solution is on the table.

“In my opinion, there are two ways, either to give that consent, so that on the basis of the consent this issue is resolved, to enable construction on that particular part, or to correct the project itself and bypass that section in that part where there is a need for that land to continue to be used by the Ministry of Defense, that is, the Armed Forces of Bosnia and Herzegovina,” says Velić.

Both highways tried: the open route was replaced by a tunnel solution, with a closed shooting range according to NATO standards and an additional 13 million marks.

“It was the recommendation of the Joint Staff of the Armed Forces of Bosnia and Herzegovina that the land is not needed for military purposes, nor does it threaten Mostar Airport… We have consent from Mostar Airport, BHDCA, BHANSA, FBiH Railways, and the Ministry of Defense. However, this was again not acceptable to the Presidency of Bosnia and Herzegovina,” Dževlan points out.

“If they think that this is no longer a problem, that it can be solved, then I don’t see why this problem would be highlighted any further. There is a possibility that it can be solved through that appropriate agreement,” added Velić.

And that’s where the bureaucratic circle closes, and this map of the fragmented route opens: from the south, a built section, then a construction site, then the record-breaking Kvanj, then a halt towards Mostar. A connected road on paper. On the field – a break of 400 square meters. Enough to turn the fastest dug tunnel into the most expensive dead end on Corridor Vc, Federalna writes.

Number of blocked Business Accounts increased to 109,121
Analysis: The average Monthly paid net Salary in the Federation of BiH
Who is a Bosnian who made H & M to raise Salaries to its Workers?
The Robotic Representatives of BiH from Singapore brought two Awards
FIPA: Economic Development Must be a Priority
Share This Article
Facebook Whatsapp Whatsapp Telegram Threads Bluesky Email Print
Share
What do you think?
Love0
Sad0
Happy0
Sleepy0
Angry0
Dead0
Wink0
Previous Article “11 in Half” in Honor of Edin Dzeko: Instead of the traditional Ten, Eleven Cevapi will be served
Next Article COM EUFOR Continues Engagement with Local Authorities in Jajce
Leave a Comment Leave a Comment

Leave a Reply Cancel reply

You must be logged in to post a comment.

Stay Connected

10.2KFollowersLike
10.1KFollowersFollow
414FollowersFollow

Latest News

Barbarez announces Squad for Matches against Sweden and Romania
October 27, 2026
US Requests Extradition of Mevlid Jasarevic Over Attack on US Embassy in Sarajevo
October 27, 2026
Ursula von der Leyen congratulates “Students List” on Victory
October 26, 2026
Acting HR Crishock meets with Ambassador of Albania Koçi
October 26, 2026
12 Parties and Coalitions in the new Composition of the FBiH House of Representatives
October 26, 2026
Great Recognition for the capital of BiH: Sarajevo declared the best Destination in the Balkans
October 26, 2026
Miners’ Protest cancelled; systemic Solution sought for Healthcare Debt
October 26, 2026
Acting High Representative Crishock meets Ambassador of Pakistan Irfan
October 26, 2026
Sarajevo breaks Tourism Records, nearly 855,000 Arrivals and a new Story for the World
October 26, 2026
Vucic after the Defeat: You will soon see changes in Relations with RS and Sarajevo
October 26, 2026
Sarajevo TimesSarajevo Times
Follow US
© 2012 Sarajevo Times. All Rights Reserved.
  • ABOUT US
  • IMPRESSUM
  • NEWSLETTER
  • CONTACT
Go to mobile version
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?