Reading: Austrian Company Strabag filed a Lawsuit against Bosnian Electric Utility Company
Share
Font ResizerAa
Sarajevo TimesSarajevo Times
Font ResizerAa
  • HOME
  • POLITICS
  • BUSINESS
  • BH TOURISM
  • INTERVIEWS
  • SPORT
  • ARTS
  • W&N
Search
  • HOME
  • POLITICS
    • BH & EU
  • BUSINESS
  • BH TOURISM
  • INTERVIEWS
    • BH & EU
    • BUSINESS
    • ARTS
  • SPORT
  • ARTS
    • CULTURE
    • ENTERTAINMENT
  • W&N
Follow US
  • ABOUT US
  • IMPRESSUM
  • NEWSLETTER
  • CONTACT
© 2012 Sarajevo Times. All rights reserved.
Sarajevo Times > Blog > BUSINESS > Austrian Company Strabag filed a Lawsuit against Bosnian Electric Utility Company
BUSINESS

Austrian Company Strabag filed a Lawsuit against Bosnian Electric Utility Company

Published January 20, 2020
Share
SHARE

 

Austrian company Strabag has filed a lawsuit before the International Court of Arbitration in Brussels, demanding payment of 40 million BAM from Elektroprivreda Bosne i Hercegovine for a dispute over the construction of the Vranduk power plant, Dnevni Avaz news portal reports.

Bosnian electricity company also considers itself as damaged because it has complied with its part of the contract and asks Strabag to pay them 30 million euros.

An Austrian company sued Bosnian Power Company over a dispute over the construction of the Vranduk hydroelectric power plant, whose work was halted in 2016, the Bosnian Electric Utility Company confirmed.

Strabag, who was the consortium leader on the 114 million BAM project, decided in early 2016 to terminate the contract because he demanded that he be provided with an additional 20 million BAM for the works, to which Elektroprivreda did not agree.

On July 2nd, it seemed like everything built at the site of the Vranduk hydroelectric power plant and Strabag workshops is done in vain after the decision is made that this company must return all to its original state.

The reason behind the decision lies in the fact that the European Bank for Reconstruction and Development (EBRD) decided that the suspension of works and the return to the original state is the best solution because Strabag exited from the project, and Euro-asphalt and Koncar failed to change the contract items with the EBRD in order to continue the works.

At the beginning of February last year, the news portal Klix.ba wrote that Euro-Asfalt will enter the consortium with Koncar, instead of Strabag. However, the problem was made by the European Bank for Reconstruction and Development (EBRD), which was supposed to issue a license to change the contractor.

The cornerstone for the construction was officially put in September 2016, and the ceremony was attended by Bakir Izetbegovic, Fahrudin Radoncic and Denis Zvizdic. At that time, HE Vranduk was presented as a capital investment for the development of hydropower and the symbol of the “great construction site”.

The information from the court was confirmed by the president of the local community Vranduk Besim Begic, who explained that the decision was made four days ago.

He added that there are little probabilities that a hydropower plant will ever be built in Vranduk after the order received by Strabag.

“We can say that 70 percent of the hydropower plant will not be at this location never, and Strabag ordered everything to be taken out of the construction site and brought to its original state, after which there will be an arbitration, “Begic said.

Unofficially, Strabag will be in minus some 20 million BAM, and in the next period, a total weight of 310 tonnes steel piles will be removed.

 

Sir James Everard from the EU Operation Headquarters in Belgium visited Sarajevo

First Prize of ‘Microsoft’ for Mobile Application of City of Bijeljina

Fifty Mine Action Professionals gathered in Sarajevo

TRB Announced Expansion Of Presence In Foreign Markets

Kosacov: Russia is paying close Attention to Developments in BiH

TAGGED:#BiH#company#electricity#elektroprivreda#strabag
Share This Article
Facebook Whatsapp Whatsapp Telegram Threads Bluesky Email Print
Share
What do you think?
Love0
Sad0
Happy0
Sleepy0
Angry0
Dead0
Wink0
Previous Article Government of Canton Sarajevo made First Step to solve Issue of Air Pollution
Next Article Thousands of Visitors on Bjelasnica Mountain despite Lack of Precipitation
Leave a Comment Leave a Comment

Leave a Reply Cancel reply

You must be logged in to post a comment.

Stay Connected

10.2kFollowersLike
10.1kFollowersFollow
414FollowersFollow

Latest News

Cvijanovic meets the Head of the Bureau for Europe and Eurasia in the US State Department
February 14, 2026
The Company from Bratunac signed a Contract with the Ministry of Defense of Azerbaijan
February 14, 2026
Defense Minister: We Have More Powerful Allies – If Dodik Declares Independence, We Will Restore the Republic of BiH
February 14, 2026
Becirovic: State Property Belongs to the State of BiH
February 14, 2026
Chairperson of CoM meets US Secretary of State Marco Rubio
February 14, 2026
CoE Commissioner for Human Rights: Politicians in Republika Srpska should refrain from hateful Speech
February 14, 2026
BiH Foreign Minister meets with the President of the Conference of European Rabbis
February 14, 2026
The US Military is preparing for possible Multi-week Military Operations against Iran
February 14, 2026
Criminal Charges against Dodik and Associates for lobbying for the Independence of the RS
February 14, 2026
Becirovic and Wadephul discuss the European Path and the Security of BiH
February 14, 2026
Sarajevo TimesSarajevo Times
Follow US
© 2012 Sarajevo Times. All Rights Reserved.
  • ABOUT US
  • IMPRESSUM
  • NEWSLETTER
  • CONTACT
Go to mobile version
adbanner
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?