Thanks primarily for the high operational readiness of all hydropower plants and favorable hydrological conditions, JP Elektroprivreda HZ HB d.d. Mostar met the production plan for 2013.
Until 28 April this year, seven hydropower production system companies produced a total of 1391 GWh electrical energy, which is more than the planned annual production for 2013 for 1376 GWh.
Apart from the aforementioned reasons, the maximum engagement and expertise of workers contributed to such good results, with the rational management and maintenance of the energy system, and good control and reduction of operating costs that could be affected.
The actual production resulted in a positive financial result with a profit on 31.3.2013 by 63.5 million KM.
Management of JP Elektroprivreda HZBHB for will continue to do everything in its power for this business trend to continue in the future, announced Elektroprivreda HZ HB.