Reading: One of the key energy Facilities worth 80 Million BAM to be built in BiH
Share
Font ResizerAa
Sarajevo TimesSarajevo Times
Font ResizerAa
  • HOME
  • POLITICS
  • BUSINESS
  • BH TOURISM
  • INTERVIEWS
  • SPORT
  • ARTS
  • W&N
Search
  • HOME
  • POLITICS
    • BH & EU
  • BUSINESS
  • BH TOURISM
  • INTERVIEWS
    • BH & EU
    • BUSINESS
    • ARTS
  • SPORT
  • ARTS
    • CULTURE
    • ENTERTAINMENT
  • W&N
Follow US
  • ABOUT US
  • IMPRESSUM
  • NEWSLETTER
  • CONTACT
© 2012 Sarajevo Times. All rights reserved.
Sarajevo Times > Blog > BUSINESS > One of the key energy Facilities worth 80 Million BAM to be built in BiH
BUSINESS

One of the key energy Facilities worth 80 Million BAM to be built in BiH

Published: April 18, 2022
Share
SHARE

The Federal Ministry of Environment and Tourism has recently submitted a request for a preliminary environmental impact assessment for the Kovanici hydro powerplant (HPP)Construction Project on the Bosna River.

This is one of the capital projects of Elektroprivreda Bosnia and Herzegovina (BiH) which is expected to increase the electricity production of the public concern from renewable, clean sources.

An investment worth 38.8 million euros

The HPP would be located 25 kilometers downstream from the town of Zenica. The installed capacity is 9.1 MW and the annual production is 46.2 Gwh.

The estimated value of the investment is 38.8 million euros, and the construction is planned from own funds and loans.

A Feasibility Study with geological exploration works, an Economic Feasibility Study and a request for a concession, as well as a Preliminary Design have already been prepared.

Elektroprivreda BiH has included this project in its plan to increase the share of electricity production from renewable resources in total production.

HPP Kovanici is one of 15 planned hydropower projects, which will ultimately harness the hydro potential of the Bosna River, from its source near Sarajevo to the entity line with Republika Srpska (RS).

Run-of-the-river hydropower plant

According to the Terms of Reference, HPP Kovanici contributes to meeting the growing demand for electricity in the country.

HPP Kovanici was designed as a classic type of run-of-the-riverplant. It is a concrete gravity overflow dam, the operator is part of the non-overflow part of the dam, and on the right and left side of the partition profile there are the wing parts of the dam – gravity blocks.

The designed dam of HPP Kovanici forms an accumulation at a length of approximately 2.60 km for Q1/100, while for the installed flow it is approximately 3.62 km long.

At the stretch of the reservoir there is the planned highway 5C, which crosses from the right to the left bank downstream from the railway bridges, Avaz writes.

E.Dz.

Agreements for Mining Gold and Iron in Gornji Vakuf Signed
International Economic Fair Mostar 2025 Set for April 8–12, Italy is a Partner Country
Breakthrough Begins on One of the Most Significant Tunnel Projects in BiH
ENERGA Fair makes Sarajevo Center of the Region again
Turks are Building a Textile Factory, 250 new jobs
Share This Article
Facebook Whatsapp Whatsapp Telegram Threads Bluesky Email Print
Share
What do you think?
Love0
Sad0
Happy0
Sleepy0
Angry0
Dead0
Wink0
Previous Article Symbol of wartime Mostar: The Basket between Life and Death
Next Article How will the Sanctions against Russia affect the Oil Refinery in BiH?
Leave a Comment Leave a Comment

Leave a Reply Cancel reply

You must be logged in to post a comment.

Stay Connected

10.2kFollowersLike
10.1kFollowersFollow
414FollowersFollow

Latest News

German Military Plane Will Fly Over BiH in the Coming Days: “Citizens Have No Reason for Panic”
May 19, 2026
CoM and ITA Board of Directors did not support the Temporary Opening of the new Gradiska Border Crossing
May 19, 2026
You Attend, Support, and Stay Longer than Planned: New OREA Art Market Scheduled for June 14
May 19, 2026
Bicakcic: The Political Situation is Fragmented, We Need Integration
May 19, 2026
Visca: NATO must transform, but BiH still has no clear Answer on whether it wants Membership
May 19, 2026
First robotic-assisted Surgeries successfully performed at KCUS
May 19, 2026
Magazinovic initiates Discussion on Femicide: We cannot say it does not concern us
May 19, 2026
Konakovic and Doughty discussed Bilateral Relations between BiH and the United Kingdom
May 19, 2026
BiH among Nineteen Countries in Europol’s Action
May 19, 2026
Contract worth 74 Million BAM signed for the Procurement of new Technologies for Elections in BiH
May 19, 2026
Sarajevo TimesSarajevo Times
Follow US
© 2012 Sarajevo Times. All Rights Reserved.
  • ABOUT US
  • IMPRESSUM
  • NEWSLETTER
  • CONTACT
Go to mobile version
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?