Reading: The Construction of a new Hydropower Plant on the Drina has been on the Cornerstone for two Years
Share
Font ResizerAa
Sarajevo TimesSarajevo Times
Font ResizerAa
  • HOME
  • POLITICS
  • BUSINESS
  • BH TOURISM
  • INTERVIEWS
  • SPORT
  • ARTS
  • W&N
Search
  • HOME
  • POLITICS
    • BH & EU
  • BUSINESS
  • BH TOURISM
  • INTERVIEWS
    • BH & EU
    • BUSINESS
    • ARTS
  • SPORT
  • ARTS
    • CULTURE
    • ENTERTAINMENT
  • W&N
Follow US
  • ABOUT US
  • IMPRESSUM
  • NEWSLETTER
  • CONTACT
© 2012 Sarajevo Times. All rights reserved.
Sarajevo Times > Blog > BUSINESS > The Construction of a new Hydropower Plant on the Drina has been on the Cornerstone for two Years
BUSINESS

The Construction of a new Hydropower Plant on the Drina has been on the Cornerstone for two Years

Published July 20, 2024
Share
SHARE

The cornerstone was laid, but after two and a half years, theconstruction hasn’t started. This is the situation with the hydroelectric power plant on the Drina, in the southeast of Bosnia and Herzegovina (BiH), which was announced as a joint project of the Republika Srpska (RS) and Serbia.

The foundation stone for the Buk Bijela hydroelectric plant was laid in May 2021, and it should have been built in the area of Foca, in the upper reaches of the Drina River, which separates Serbia and BiH.

It is a joint electric power project of the RS and Serbian power companies, worth around 250 million euros.

Last summer, three Chinese bids were submitted for the construction of the hydroelectric power plant. However, the contractor has not been chosen to date and everything has been extended until the spring of 2024.

What disputes precede construction?

The signing of contracts with Chinese companies became questionable due to the unresolved dispute about concessions, which was initiated more than two years ago before the Constitutional Court of BiH.

This is not the only dispute that hinders the construction of the “Buk Bijela” hydroelectric power plant. The second was launched before UNESCO, initiated by Montenegro, concerned about its possible negative impact on the Durmitor National Park.

The Constitutional Court of BiH is waiting for the Commission’s decision

The dispute before the Constitutional Court was initiated after the RS Government granted a concession for hydropower plants on the Drina River.

In mid-2021, more than 20 representatives of the state Parliament addressed that court, warning that the hydroelectric power plants “are planned on state property that the RS entity has no right to dispose of”.

After that, the Constitutional Court determined that it was a dispute about concessions between BiH and the RS entity and that it was not competent to resolve it by itself.

The case was transferred to the BiH Concessions Commission, which is competent to assess whether a concession was granted in accordance with the Constitution of BiH, but this has not yet been done, Radio Slobodna Evropa writes.

E.Dz.

 

Increase in Production of Drinking Milk and Products in Bosnia and Herzegovina

Wizz Air has added Four new Routes from Banja Luka Airport

SPARK announces Innovations, Electric Vehicles and Robots

285 Million BAM allocated for Pensioners in the Federation of BiH

Increase of Price of Coffee in BiH as of Today

Share This Article
Facebook Whatsapp Whatsapp Telegram Threads Bluesky Email Print
Share
What do you think?
Love0
Sad0
Happy0
Sleepy0
Angry0
Dead0
Wink0
Previous Article A Miracle from Mostar – Identical Triplets Renea, Izabela, and Antea
Next Article A Man in the RS Police Uniform was filmed in a betting Shop: He cursed Country and Laws
Leave a Comment Leave a Comment

Leave a Reply Cancel reply

You must be logged in to post a comment.

Stay Connected

10.2kFollowersLike
10.1kFollowersFollow
414FollowersFollow

Latest News

Members of the Presidency of BiH attend the Opening ceremony of the Antalya Diplomatic Forum
April 17, 2026
Cost of Living rises faster than Wages as Citizens Struggle with growing Inequality
April 17, 2026
Iran declares Strait of Hormuz free for Commercial Navigation
April 17, 2026
BiH Delegation holds Meeting with the Director of the Defense Security Cooperation Agency
April 17, 2026
BiH FM met with the Minister of State at the Ministry of Foreign Affairs of Singapore
April 17, 2026
HDZ President calls for a Single Croat Candidate
April 17, 2026
Request for Measures for Debevac and Mehmedagic
April 17, 2026
Tuzla introduces Special Fees for Games of Chance
April 17, 2026
EU considers halting Funding to HJPC over Changes in Asset Verification of Judges and Prosecutors
April 17, 2026
What is the Average Monthly paid Net Salary per Employee in the Federation of BiH?
April 17, 2026
Sarajevo TimesSarajevo Times
Follow US
© 2012 Sarajevo Times. All Rights Reserved.
  • ABOUT US
  • IMPRESSUM
  • NEWSLETTER
  • CONTACT
Go to mobile version
adbanner
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?