Reading: First phase of the construction of ”Vijenac” tunnel is being finished
Share
Font ResizerAa
Sarajevo TimesSarajevo Times
Font ResizerAa
  • HOME
  • POLITICS
  • BUSINESS
  • BH TOURISM
  • INTERVIEWS
  • SPORT
  • ARTS
  • W&N
Search
  • HOME
  • POLITICS
    • BH & EU
  • BUSINESS
  • BH TOURISM
  • INTERVIEWS
    • BH & EU
    • BUSINESS
    • ARTS
  • SPORT
  • ARTS
    • CULTURE
    • ENTERTAINMENT
  • W&N
Follow US
  • ABOUT US
  • IMPRESSUM
  • NEWSLETTER
  • CONTACT
© 2012 Sarajevo Times. All rights reserved.
Sarajevo Times > Blog > BUSINESS > First phase of the construction of ”Vijenac” tunnel is being finished
BUSINESS

First phase of the construction of ”Vijenac” tunnel is being finished

Published: February 28, 2013
Share
SHARE

Group of BiH construction companies, led by Euro-Asfalt Sarajevo, has finished the first phase of constructing the ”Vijenac” tunnel, which consists of digging up the tunnel and setting the protection.

Manager of Euro-Asfalt Hamed Ramić said to FENA: ”Currently we are digging the last meters of the tunnel in the left tube, which will be finished today, and today, on the Day of Independence of BiH, the tunnel would be officially excavated.”

The tunnel ”Vijenac” is currently the most demanding construction project at the corridor 5C,says Ramić and it is also the largest tunnel that a BiH company has excavated.

In the second tube, additional 300 metres needs to be excavated and it will be finished in 20 days.

”According to contract, the deadline for finishing the first phase of works is the end of the March and we will comply with the deadline”, added Ramić.
Apart from Euro-Asfalt, ŽGP Sarajevo, Hidrogradnja Sarajevo, Entea Sarajevo and Butmir Sarajevo also worked on the tunnel.

Ramić said that more than 300 workers work on the tunnel in three shifts, and that more than 1000 people are engaged on the construction the tunnel which will be 3 km long.

The excavation is being done by Austrian method, and various engineers are present at the digging sites.

Ramić added that tunnel building is very precise, and that all the engineers and investors are satisfied with the quality of the job.

The tunnel will be equipped with the most modern equipment, and the road Sarajevo-Zenica will be shortened by 6 kilometres. The value of the 1st phase of the works is 18 million EUR.

”Group of BiH companies will successfully finish the job before the deadline and show that they are capable doing the most demanding construction projects and justify the trust of investors. It is particularly important that with these jobs, BiH companies get a recommendation for future jobs”, said Ramić.

First cars should pass in 2014.

Foreign Investors Bought Land For Construction of Residential Neighborhoods in Municipality Ilijaš
Big Champion Cup at Novi Sad Agricultural Fair for Fruit Brandy “BMB Delta” from Jablanica
’Terra Sana’ from Sanski Most Started Production of Essential Oils
650 Million BAM of Foreign Investments in Bosnia and Herzegovina
Domestic Shopping Centre Robot opened: Investment worth 10 Million BAM
Share This Article
Facebook Whatsapp Whatsapp Telegram Threads Bluesky Email Print
Share
What do you think?
Love0
Sad0
Happy0
Sleepy0
Angry0
Dead0
Wink0
Previous Article Bilateral Defense Cooperation for 2013 Signed Between BiH and Norway
Next Article N. Poposki: Strenghten the economic relations and regional cooperation
Leave a Comment Leave a Comment

Leave a Reply Cancel reply

You must be logged in to post a comment.

Stay Connected

10.2kFollowersLike
10.1kFollowersFollow
414FollowersFollow

Latest News

Second Victim of the Shooting in Kiseljak dies
May 18, 2026
Exhibition “Erasmus Spain and BiH – a Journey of Culture and Creativity” opened
May 18, 2026
Gunman in Kiseljak Dies After Killing One and Seriously Injuring Another
May 18, 2026
EUFOR Commander Praises Irish Contribution to Peace and Stability in BiH
May 18, 2026
First comprehensive Cancer Prevention Research completed in BiH with EU Support
May 18, 2026
Nebojsa Vukanovic confirms His Candidacy for the Member of BiH Presidency
May 18, 2026
Members of the BiH Border Police prevent the Smuggling of 14 Foreign Citizens
May 18, 2026
Federal Police Administration arrests Four Persons in Sarajevo
May 18, 2026
Young Innovator Ahmed Guso wins First Place at international Competition in Indonesia
May 18, 2026
11 Mountain Peaks over 2,000 Meters, Eight “Mountain Eyes,” and 17 Icy Rivers and Streams in BiH
May 18, 2026
Sarajevo TimesSarajevo Times
Follow US
© 2012 Sarajevo Times. All Rights Reserved.
  • ABOUT US
  • IMPRESSUM
  • NEWSLETTER
  • CONTACT
Go to mobile version
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?