Reading: OLAF investigates FBiH Motorways: Will the Investigation slow down the Construction of Corridor Vc?
Share
Font ResizerAa
Sarajevo TimesSarajevo Times
Font ResizerAa
  • HOME
  • POLITICS
  • BUSINESS
  • BH TOURISM
  • INTERVIEWS
  • SPORT
  • ARTS
  • W&N
Search
  • HOME
  • POLITICS
    • BH & EU
  • BUSINESS
  • BH TOURISM
  • INTERVIEWS
    • BH & EU
    • BUSINESS
    • ARTS
  • SPORT
  • ARTS
    • CULTURE
    • ENTERTAINMENT
  • W&N
Follow US
  • ABOUT US
  • IMPRESSUM
  • NEWSLETTER
  • CONTACT
© 2012 Sarajevo Times. All rights reserved.
Sarajevo Times > Blog > BUSINESS > OLAF investigates FBiH Motorways: Will the Investigation slow down the Construction of Corridor Vc?
BUSINESS

OLAF investigates FBiH Motorways: Will the Investigation slow down the Construction of Corridor Vc?

Published: July 19, 2026
Share
SHARE

The continuation of the construction of highways in the Federation of Bosnia and Herzegovina could be questioned after it was confirmed that representatives of the European Anti-Fraud Office (OLAF) in the Public Enterprise Autoceste FBiH conducted official activities to collect documentation.

It is about documentation related to projects on Corridor Vc and public procurement procedures carried out according to international procedures in the period from 2018 to 2022.

Autoceste FBiH reminds that the deadlines for the completion of certain sections of Corridor Vc have been postponed several times, and they state that now is an opportunity to shed light on all the circumstances that accompanied the implementation of certain infrastructure projects.

“Irregularities that may have arisen over a long period of time cannot be eliminated in one move, nor can all answers be obtained in one day,” said Autocest FBiH.

Investigative journalists have been reporting on possible irregularities and corruption during the construction of sections of Corridor Vc for years.

Fokus.ba journalist Amil Dučić points out that this is not the first time that OLAF exempts documentation from the FBiH Highway.

“These are projects financed by European investment banks. In this case, the focus is on the section Poprikuš – Nemila. In research articles, we pointed out suspicions of corrupt activities, especially when it comes to the excessive allocation of funds for the contractor Cengiz, which was allocated 54 million KM for one part of the Golubinje tunnel. Also, on the section Ozimica – Poprikuša, which has not even started construction yet, there was an exchange of bids and suspicions of corruption during the awarding of construction supervision, which OLAF is also investigating,” said Dučić.

Transparency International BiH warns that public companies are especially exposed to the risk of corruption due to the large financial resources at their disposal, but also that the supervision of their work is not efficient enough.

“When information about irregularities appears, it is generally not investigated until there is serious pressure from the international institutions on which these companies depend, because these institutions are their financiers,” said Damjan Ožegović from Transparency International BiH.

Dučić believes that the consequences of possible corrupt activities are ultimately felt by the citizens the most.

“If we look at the history of highway construction from 2001 until today, almost all deadlines have been exceeded. It used to be said that the highway would be completed in 2009, then in 2013, and then in 2016. I think that we should no longer come out with deadlines, given that the projects are bogged down in corruption scandals. Several directors were arrested, and the current management is facing serious charges,” Dučić pointed out.

Suspicions of irregularities are now the subject of checks by the European Anti-Fraud Office, and the results of the investigation could be important not only for determining eventual liability, but also for the continuation of the implementation of infrastructure projects on Corridor Vc, BHRT writes.

What is the Amount of Debt to the Tax Administration of the FBiH?
The New Labour Law in Force from the middle of the Month?
Energoinvest On The Ban On Importing Russian Gas: Implementation Of That EU Decision In BiH Is From January
Over 7.300 Medical Professionals have left BiH
For the First Time in 60 Years: The Reconstruction of the Tram Line starts in Sarajevo
Share This Article
Facebook Whatsapp Whatsapp Telegram Threads Bluesky Email Print
Share
What do you think?
Love0
Sad0
Happy0
Sleepy0
Angry0
Dead0
Wink0
Previous Article Judo Tournament Sarajevo European Open 2026 has started
Next Article The Majority is divided, Laws are Pending – is there a Compromise?
Leave a Comment Leave a Comment

Leave a Reply Cancel reply

You must be logged in to post a comment.

Stay Connected

10.2KFollowersLike
10.1KFollowersFollow
414FollowersFollow

Latest News

BiH FM with the Ambassador of Saudi Arabia: Strong mutual Support for Sovereignty and Territorial Integrity
October 12, 2026
Dodik: We continue to work with the HDZBIH, the Constitution of the BiH Presidency will follow
October 12, 2026
No More Staying at Home on Election Day? Arnautovic Proposes Compulsory Voting in BiH and Voting Rights at Age 16
October 12, 2026
Interview with Sabina Cudic: Excuses Are Not Responses, Voters Demand Better and More
October 12, 2026
Telekom Srbija: Our International Business Is Built on the Rule of Law, Transparency and Legitimate Business Interests
October 12, 2026
BiH FM to meet with the ambassador of Saudi Arabia over the controversial Allegations of Dodik’s Lobbyists
October 12, 2026
Historic Night: Igman Burch defeated Mladost in front of his Fans for a perfect Start in the Elite
October 12, 2026
Continental Strategy confirms Telekom Srbija has been its Client since January 2026
October 12, 2026
New Order from the Central Election Commission of BiH to the Main Counting Centre
October 12, 2026
Dodik’s Lobbyists claim Officials of Saudi Arabia and Israel supported the Independence of RS
October 12, 2026
Sarajevo TimesSarajevo Times
Follow US
© 2012 Sarajevo Times. All Rights Reserved.
  • ABOUT US
  • IMPRESSUM
  • NEWSLETTER
  • CONTACT
Go to mobile version
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?