Reading: Who will be held accountable for the 50 Million Euros Damage committed on the Highway Section
Share
Font ResizerAa
Sarajevo TimesSarajevo Times
Font ResizerAa
  • HOME
  • POLITICS
  • BUSINESS
  • BH TOURISM
  • INTERVIEWS
  • SPORT
  • ARTS
  • W&N
Search
  • HOME
  • POLITICS
    • BH & EU
  • BUSINESS
  • BH TOURISM
  • INTERVIEWS
    • BH & EU
    • BUSINESS
    • ARTS
  • SPORT
  • ARTS
    • CULTURE
    • ENTERTAINMENT
  • W&N
Follow US
  • ABOUT US
  • IMPRESSUM
  • NEWSLETTER
  • CONTACT
© 2012 Sarajevo Times. All rights reserved.
Sarajevo Times > Blog > BUSINESS > Who will be held accountable for the 50 Million Euros Damage committed on the Highway Section
BUSINESS

Who will be held accountable for the 50 Million Euros Damage committed on the Highway Section

Published: March 22, 2024
Share
SHARE

As it was found out, the Prosecutor’s Office of the Herzegovina-Neretva Canton (HNC) sent the current director of the Highwaysof the Federation of Bosnia and Herzegovina (FBiH), Denis Lasic, an invitation to a hearing due to the investigation into illegalities on the section of the highway on Corridor 5C Vranduk-Ponirak.

As it was unofficially confirmed, as part of this case, the previous director of the FBiH Highways, Elmedin Voloder, has already been questioned. Also, as part of the investigation, a number of people from the FBiH Highways, as well as companies that were involved in the implementation of this section, were heard.

The police did their job

The Federal Police Administration, which is extensively investigating crime in this section, will soon submit its report to the HNC Prosecutor’s Office. Earlier it was confirmed that the Federal Police Administration was asked to undertake certain investigative actions within their competence and to carry out checks of the allegations from the report, as well as an analysis of the submitted documentation and other operative and investigative actions, all with the aim of establishing the correct factual situation and collecting material evidence.

The HNC Prosecutor’s Office formed the “Vranduk-Ponirak” case back in October 2022, and this happened after journalists wrote about malfeasance in the construction of the Vranduk-Ponirak section on Corridor 5C Highway near Zenica.

The case is investigating information that points to organized criminogenic activities such as falsification of documents and other manipulations, that is, conscious price increase, i.e. costs of the total activities in the sub-section, all in order to bring multi-million dollar benefits to individuals.

Lasic recently said that, after a long stoppage, work on this section will soon start again, adding that the new administration headed by him suspended this project after it was appointed because they found that the planned amount (around 150 million euros with additional credit) was spent on a third of the project.

Individuals from Hering and Azvirt

According to unofficial information, individuals stated at the hearing at the HNC Prosecutor’s Office, as well as at the supervisory authority for this section, that the damage caused to this section amounts to more than 50 million euros. Namely, the companies Azvit from Azerbaijan and Hering from Siroki Brijeg were engaged as contractors on this section. As sources involved in the investigation told, individuals from both of these companies are also under scrutiny.

It is important to mention that the contract for the construction of the section Poprikuse – Zenica north (Donja Gracanica), whose subdivision is Vranduk – Ponirak, was signed on May 15th, 2019. The supervision of the execution of the works is carried out by the consortium DRI Investment Management d.o.o (Slovenia) – DIVEL d.o.o Sarajevo (BiH).

This section was supposed to be completed in August 2021. The annex to the contract, which was signed on January 26th of this year, defined a new deadline for the completion of the works, namely March 31st, 2026, N1 writes.

Photo: archive

New Projects on Corridor 5C agreed?
“Pitching your Product” Workshop successfully held
The former BiH Giant needs Workers from Asia to start Production
FBiH Budget of 5.6 Billion BAM is the largest so far
What is the average monthly net Salary in BiH?
Share This Article
Facebook Whatsapp Whatsapp Telegram Threads Bluesky Email Print
Share
What do you think?
Love0
Sad0
Happy0
Sleepy0
Angry0
Dead0
Wink0
Previous Article More Children killed in four Months in Gaza than in four Years of Wars around the World
Next Article Is Netanyahu hoping to escalate the Conflict with Hezbollah to stay in Power?
Leave a Comment Leave a Comment

Leave a Reply Cancel reply

You must be logged in to post a comment.

Stay Connected

10.2KFollowersLike
10.1KFollowersFollow
414FollowersFollow

Latest News

Military Exercise ‘Immediate response 26’, more than 1,200 Members of the Armed Forces of BiH participate
October 17, 2026
The Tax Administration of FBiH imposed fines of almost 376,000 BAM
October 17, 2026
Covic: Election Law Is a Priority, Government Should Be Formed as soon as possible
October 17, 2026
“Sarajevo Safari”: Austria to decide on possible Indictment against Two Citizens
October 17, 2026
Sarajevo Water Utility Company informs Consumers about Night Reductions
October 17, 2026
The Central Election Commission of BiH orders a Control Count at 89 Polling Stations
October 17, 2026
BiH in the Focus of the Republic of Croatia’s New Aid Program until 2030
October 17, 2026
Cvijanovic: Filipovic and I share the same Stance on certain Issues, but I am not forming an Alliance with Anyone
October 16, 2026
What is the average Monthly Net Salary in the Federation of BiH?
October 16, 2026
CEC BiH: Counting of mail-in Ballots begins Today
October 16, 2026
Sarajevo TimesSarajevo Times
Follow US
© 2012 Sarajevo Times. All Rights Reserved.
  • ABOUT US
  • IMPRESSUM
  • NEWSLETTER
  • CONTACT
Go to mobile version
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?