Reading: Audit Reveals Irregularities in FBiH Highways: Over Half a Billion BAM Spent on Just Four Sections
Share
Font ResizerAa
Sarajevo TimesSarajevo Times
Font ResizerAa
  • HOME
  • POLITICS
  • BUSINESS
  • BH TOURISM
  • INTERVIEWS
  • SPORT
  • ARTS
  • W&N
Search
  • HOME
  • POLITICS
    • BH & EU
  • BUSINESS
  • BH TOURISM
  • INTERVIEWS
    • BH & EU
    • BUSINESS
    • ARTS
  • SPORT
  • ARTS
    • CULTURE
    • ENTERTAINMENT
  • W&N
Follow US
  • ABOUT US
  • IMPRESSUM
  • NEWSLETTER
  • CONTACT
© 2012 Sarajevo Times. All rights reserved.
Sarajevo Times > Blog > BUSINESS > Audit Reveals Irregularities in FBiH Highways: Over Half a Billion BAM Spent on Just Four Sections
BUSINESS

Audit Reveals Irregularities in FBiH Highways: Over Half a Billion BAM Spent on Just Four Sections

Published October 2, 2025
Share
SHARE

Under threat of insolvency, without a clearly defined source of financing, with 138 kilometers completed, and 2.3 billion marks spent. These are parts of the audit report on the work of the Public Company Autoceste Federaždenija, which spent more than half a billion marks on four sections from the originally planned contract. While prices are rising and credit funds are being used beyond plan, the question is when Corridor 5c will stop being a scandal.

Due to multiple changes in the contract, the costs for the construction of these four sections have increased by an additional 255 million euros or 19.5 million marks per kilometer built.

“Because of the above, we have not gained reasonable assurance that the responsible persons, management bodies, each within their jurisdiction, have taken appropriate actions to protect the Company from negative economic consequences, which have arisen due to failure to act on concluded contracts and the creation of additional costs due to project changes,” the audit report states, among other things.

All sections that were supposed to be completed, but never were. The pace is seven years – less than five kilometers. The Poprikuša – Nemila section, the contract was signed five years ago, the construction deadline was last year. Nemila – Vranduk, the completion deadline was exceeded by more than a year. The Vranduk – Ponirak section should have been completed four years ago. It is the subject of investigation, i.e. judicial authorities, where the former management is accused of tender fraud and inflating the price of this section, which is as much as 154 million marks higher than the originally contracted one.

“There was an explosion of costs here. In order for this to happen, almost everyone must participate – from the contractors to the motorway managers themselves. At the time, Elmedin Voloder was at the helm of the motorway and an investigation is underway against him,” says journalist Amil Dučić.

The contract was signed six years ago, the construction deadline expired four years ago, and half of the work done, a total of five kilometers, has spent all 76.5 million euros, which was the money for the entire section.

Kvanj – Buna Tunnel. Since 2018, there has been a tug-of-war over who will get the job. Because of this, and three administrations later, two annulled procedures, one also due to an investigation, the deadline for completion was missed, and the construction price increased by as much as 110 million marks.

“Even the European Anti-Fraud Office OLAF got involved. According to OLAF, the director then directly interfered in the work of the commission and selected the contractor,” Dučić points out.

The current management of Autocesta FBiH rejects the auditors’ allegations of unscrupulous business practices and the use of public funds, claiming that they are unfounded, and their work is in the function of protecting the company from damage.

“It is true that the construction deadlines on the sections were extended, as well as an increase in the contracted value, but for objective and justified reasons, which are not stated in the report, and these are changes in conditions on the ground, unresolved property and legal affairs, inflation, the price of materials, as well as insufficiently defined elements of the project documentation,” Autocesta FBiH states.

“The fact is that they did inherit huge problems and machinations from the previous administration. Among other things, I reported that on the Poprikuše – Nemila section, in the selection of supervision, and that is a section that has yet to start construction, there was a substitution of bids. They canceled that tender three times. So, we also have current corruption on the scene, not just corruption from some previous time,” says Dučić.

While construction prices are rising, the problem is also paying multi-million-dollar penalties for taken but unused money from foreign creditors. This is also the practice of the current Administration, which has requests for new debt of more than a billion marks, where, as the auditors warn, the money will once again be taken, and the section will not be ready for construction – which are the penalties that are being announced.

“The EIB and EBD are quite concerned about the implementation of funds, which is why they have launched internal investigations. They have partly confirmed this to me. And according to my information, an investigation is also underway in the EU into the spending of EU funds on certain sections,” says Dučić.

This is the framework in which the construction of Corridor 5c is taking place, where for more than two billion marks spent and twenty years of construction we have obtained 138 kilometers of Corridor. Scandals, investigations, missed deadlines, fabricated prices and sections like road monuments that lead nowhere, Federalna writes.

“Konzum“ celebrated 10th Anniversary

Bellissima is Successful B&H Story That Started in 1997

Bosnian Company “Kristin Mod” exports all of its Products to Paris

Where do the most unsafe Products in BiH come from?

How much do the Citizens of Bosnia and Herzegovina save?

Share This Article
Facebook Whatsapp Whatsapp Telegram Threads Bluesky Email Print
Share
What do you think?
Love0
Sad0
Happy0
Sleepy0
Angry0
Dead0
Wink0
Previous Article Strong Earthquake shook Buildings in Turkey’s largest City
Next Article Ambassador of Indonesia to BiH met with the Mayor of Konjic
Leave a Comment Leave a Comment

Leave a Reply Cancel reply

You must be logged in to post a comment.

Stay Connected

10.2kFollowersLike
10.1kFollowersFollow
414FollowersFollow

Latest News

Exchange of Letters on the 30th Anniversary of Diplomatic Relations between BiH and Japan
February 20, 2026
BiH’s Specialized Industry Records Steady Export Growth Over the Past Five Years
February 20, 2026
Cassis and Konakovic: Transparent Elections are crucial for Democracy in BiH
February 20, 2026
The US Supreme Court overturned Trump’s Tariffs
February 20, 2026
Becirovic-Cassis: OSCE remains dedicated to preserving Peace and Stability in BiH and the Region
February 20, 2026
BiH Photographer Bakir Niksic passes away: A Man who saw Beauty in ordinary People
February 20, 2026
Protection of Buna River instead of Small Hydroelectric Power Plants
February 20, 2026
Government of FBiH Approves Adjustment of Pensions in the Amount of 11.26 Percent
February 20, 2026
POSKOK officially took over the Donja Jablanica Case
February 20, 2026
Kristo Urges Western Balkan PMs to Present Unified EU Strategy Amid Escalating Transport Disputes
February 20, 2026
Sarajevo TimesSarajevo Times
Follow US
© 2012 Sarajevo Times. All Rights Reserved.
  • ABOUT US
  • IMPRESSUM
  • NEWSLETTER
  • CONTACT
Go to mobile version
adbanner
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?