Reading: Work has begun on the most expensive Section of the Highway in BiH
Share
Font ResizerAa
Sarajevo TimesSarajevo Times
Font ResizerAa
  • HOME
  • POLITICS
  • BUSINESS
  • BH TOURISM
  • INTERVIEWS
  • SPORT
  • ARTS
  • W&N
Search
  • HOME
  • POLITICS
    • BH & EU
  • BUSINESS
  • BH TOURISM
  • INTERVIEWS
    • BH & EU
    • BUSINESS
    • ARTS
  • SPORT
  • ARTS
    • CULTURE
    • ENTERTAINMENT
  • W&N
Follow US
  • ABOUT US
  • IMPRESSUM
  • NEWSLETTER
  • CONTACT
© 2012 Sarajevo Times. All rights reserved.
Sarajevo Times > Blog > BUSINESS > Work has begun on the most expensive Section of the Highway in BiH
BUSINESS

Work has begun on the most expensive Section of the Highway in BiH

Published December 3, 2023
Share
SHARE

Of the 650 kilometers of the Pan-European highway on Corridor 5c, from Budapest to the Adriatic Sea, 317 kilometers are through Bosnia and Herzegovina. So far, 126 kilometers have been built. In addition to the section Putnikovo Brdo – Medakovo, on the inter-entity line near Doboj, work also began on the longest and most expensive contracted section Medakovo – Ozimice. According to the contractors, despite the increased costs and numerous technical challenges, the works should be completed by the middle of 2026.

8.5 kilometers long, the Putnikovo Brdo – Medakovo section, along with six bridges, also includes regulation of the riverbeds of the Usora, Tešanjka and Trebačka rivers in a length of six kilometers.

“Due to the presence of rivers, there is no shortage of challenges, we already have several of them. We are currently in one of those locations where we had to overcome certain technical challenges”, says Jasmin Bučo, general manager of Euroasfalt.

It is about the “Hrastik” tunnel, where the modern, so-called the “Austrian” method of construction to avoid the displacement of the international transmission line, but also the local road.

At the same time, work on the longest, but also the most expensive section of the highway on Corridor 5c through Bosnia and Herzegovina was opened. Namely, we are talking about the Medakovo-Ozimica section with a total length of 22 kilometers and a value of over 420 million euros including VAT.

On this section, which passes through the municipalities of Tešanj, Maglaj and Žepče, which is being built by the Turkish “Cengiz İnşaat”, as many as 25 smaller and larger bridges, two viaducts, and one interchange will be built.

“Currently, works are being carried out in a length of 16 kilometers worth over 900 million marks. About two percent of the area of the Tešanj municipality is occupied by the construction site at the moment”, points out Suad Huskić, head of the Tešanj Municipality.

This share is financed by the European Investment Bank. The war in Ukraine and inflation adversely affect the financing of the construction of this demanding section.

“That gap is now being bridged in the negotiations with the financiers,” says Ermin Handžar, head of the Construction Service at JP Autoceste FBiH.

Despite the bad weather, the works are in progress. The section Putnikovo Brdo – Medakovo worth 167 million euros should be completed on June 1, 2025, and Medakovo – Ozimice a year later.

“This is how we have been solving problems so far – if we continue, I think we can meet the deadlines,” says Bučo.

“In a technical sense, on the critical road on this second section is the ‘Crni vrh’ tunnel, which is 2.2 kilometers long, but our experience tells us that we can bridge it in that period,” says Handžar.

In 2024, the construction of 54 kilometers of highway through Bosnia and Herzegovina is planned.

Photo: illustration

BiH Company is working on the Elimination of Defects on the biggest Bridge

Zvizdic and Bevanda met with the Executive Director of the IMF in Washington

The glass Portals of the Bakery were damaged at two Locations after Swine Meat Scandal

Governor of Central Bank of BiH: Delays in the formation of Governments may slow Structural Reforms

Valuable Investment: Bosnian Woman and American Businessman launched modern Dairy in Gorazde

Share This Article
Facebook Whatsapp Whatsapp Telegram Threads Bluesky Email Print
Share
What do you think?
Love0
Sad0
Happy0
Sleepy0
Angry0
Dead0
Wink0
Previous Article Bombing of Gaza continues, Increasing Pressure to protect the Civilian Population
Next Article The Israeli Army demands the Evacuation of the Settlement in the south of the Gaza Strip
Leave a Comment Leave a Comment

Leave a Reply Cancel reply

You must be logged in to post a comment.

Stay Connected

10.2kFollowersLike
10.1kFollowersFollow
414FollowersFollow

Latest News

Iran’s President calls on Countries in the Region not to allow ‘Enemies to wage war’ from their Territories
March 29, 2026
There is no Risk of Flooding in the Banja Luka Area
March 29, 2026
10th Edition of Porsche Sarajevo Coffee Fest Celebrates Coffee Passion in Sarajevo
March 29, 2026
Feminist Tourist Tour about Women who shaped Mostar throughout History
March 29, 2026
SDA – BiH is the Owner of State Property, we do not accept other Solutions
March 29, 2026
A Month of War with Iran: Difficult Decisions before Donald Trump
March 29, 2026
Strong Earthquake hit Japan, no Tsunami Warning
March 29, 2026
Bosnia And Herzegovina Third In The Region By Monetary Gold Reserves
March 29, 2026
Three Journalists killed in an Israeli Attack on Lebanon
March 29, 2026
Una-Sana Canton without Electricity and Water over Snowfall
March 29, 2026
Sarajevo TimesSarajevo Times
Follow US
© 2012 Sarajevo Times. All Rights Reserved.
  • ABOUT US
  • IMPRESSUM
  • NEWSLETTER
  • CONTACT
Go to mobile version
adbanner
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?