Reading: The Highway Through B&H: New Sections in 2015 with an Investment of Half a Billion BAM
Share
Font ResizerAa
Sarajevo TimesSarajevo Times
Font ResizerAa
  • HOME
  • POLITICS
  • BUSINESS
  • BH TOURISM
  • INTERVIEWS
  • SPORT
  • ARTS
  • W&N
Search
  • HOME
  • POLITICS
    • BH & EU
  • BUSINESS
  • BH TOURISM
  • INTERVIEWS
    • BH & EU
    • BUSINESS
    • ARTS
  • SPORT
  • ARTS
    • CULTURE
    • ENTERTAINMENT
  • W&N
Follow US
  • ABOUT US
  • IMPRESSUM
  • NEWSLETTER
  • CONTACT
© 2012 Sarajevo Times. All rights reserved.
Sarajevo Times > Blog > OUR FINDINGS > OTHER NEWS > The Highway Through B&H: New Sections in 2015 with an Investment of Half a Billion BAM
OTHER NEWS

The Highway Through B&H: New Sections in 2015 with an Investment of Half a Billion BAM

Published May 29, 2015
Share
SHARE

highwayThe Public Enterprise Motorways of FB&H ensured half a billion BAM for a new investment cycle of building 20 kilometers of highway, which should begin in 2015, it was confirmed in this company.

“This is very important for the continuity of the construction. It is about constructing two sections. For the section Počitelj – Međugorje, 11 kilometers in length, 100 million euros were secured from the European Investment Bank (EIB). This is a very favorable credit line intended for the infrastructure projects with a repayment period of 25 years, a grace period of five years and an interest rate of less than 1 percent”, it was announced from the  Public Enterprise Motorways of FB&H.

The most interesting object on the Počitelj – Međugorje section will be the Počitelj Bridge, the longest bridge on the Corridor 5C. It will be 945 meters long with the maximum height of 100 meters above ground with monolith pillars and a 147 meters long superstructure between them. It will be built with the same technology as the 500 meters long Studenčica Bridge.

Other significant objects which will be built on this section are: two-pipe tunnel (1.200 meters), Počitelj interchange, Počitelj pay toll, inclusion to the M-17 highway, three viaducts, three underpasses and one overpass.

“The evaluation of the offers is in progress, followed by the tender announcement. We predict that the works on new 11 kilometers of the highway to the south will begin in summer this year. The deadline for the construction is 30 months from the contract signing. The funds are granted by the EIB, amounting to 100 million euros”, it was stated from the Public Enterprise Motorways of FB&H.

They stress that the new stretches of the highway to the south will be of great importance for the tourism and the economy.

“The positive effects will be reflected in the joint of Počitelj and Međugorje, and Mostar will approach the regional centers in neighboring Croatia and other EU countries as well”, it was emphasized from the Public Enterprise Motorways of FB&H.

For the section Zenica South – Zenica North (10 km long), financial means are secured from the OFID fund amounting to 60 million euros and 30 million euros from the Kuwait Fund for Reconstruction and Development.

”Construction works on one of the two lots on this section have already started. The procedure of verification of another 50 million euros necessary to complete 9 kilometers of the Zenica South-Zenica North section, along with the bridge that will connect the Zenica city detour with the highway, is in progress”, it was stressed from this enterprise.

The funds were previously negotiated with the Kuwait Fund for Reconstruction and Development and are required in 2017.

“Due to the optimization of the cash flow of companies, this procedure has been launched only recently. On the other hand, the Public Enterprise Motorways of FB&H received the approval of the Federal Government in the three-year business plan for further action on the construction of the highway on Corridor 5C through two modes”, it was announced from the Public Enterprise Motorways of FB&H.

The first model includes the continuation of the construction through further cooperation with international financial institutions.

“It is about the use of long-term infrastructure funding with very favorable repayment terms and interest rate. For this model, it is necessary to provide additional income for the Public Enterprise Motorways of FB&H. In this regard, last year it was agreed to increase the excise tax on the construction of the highway with the International Monetary Fund. This move would equal the excise amount to the countries in the region, which would bring the company an additional 1.2 billion BAM for the construction. It is planned to earmark these funds for the construction of the highway towards the Adriatic Coast”, it was emphasized from the Public Enterprise Motorways of FB&H.

The second model is the construction through concessions. The Model “Design-Finance-Build-Operate and return to the Purchaser” foresees the construction to the north of the country during 25 years.

 

(Source: klix.ba)

Sarajevan Adnan Ceric earns Money by playing Games on YouTube

”Merhamet” donated 2 million BAM to Flood Victims

Earthquake hit Ljubinje Area in Bosnia-Herzegovina

Federation of Bosnia and Herzegovina “earned” Two Million BAM by replacing a Prison Sentence with a Fine

Five Hundred Migrants transported from Tuzla City Centre to Blazuj Barracks

Share This Article
Facebook Whatsapp Whatsapp Telegram Threads Bluesky Email Print
Share
What do you think?
Love0
Sad0
Happy0
Sleepy0
Angry0
Dead0
Wink0
Previous Article Domestic Jaffa Ltd. Launches Cherries to the Russian Market
Next Article Special Forces from Israel to arrive to the match in Zenica?
Leave a Comment Leave a Comment

Leave a Reply Cancel reply

You must be logged in to post a comment.

Stay Connected

10.2kFollowersLike
10.1kFollowersFollow
414FollowersFollow

Latest News

Femicide: Where is the Line between Information, Responsibility and Victimization?
May 5, 2026
UN Debates BiH as Republika Srpska Government Levels Serious Radicalism Accusations in Report
May 5, 2026
COM EUFOR meets Prime Minister of the Federation of BiH
May 5, 2026
School in Citluk banned Cell Phones and introduced strict Rules
May 5, 2026
IDU Forum 2026: BiH must take Advantage of the shifting Developments in Europe
May 5, 2026
Remembrance Day for 1,601 killed Children of besieged Sarajevo marked
May 5, 2026
Cantonal Court sentenced Four Persons to 41 Years in Prison over Distribution of Narcotics
May 5, 2026
Over 355 Million BAM allocated for Pensioners in the Federation of BiH
May 5, 2026
Civil Servants, Police Officers, Military Personnel in BiH can receive Gifts up to 300 BAM
May 5, 2026
Sarajevo expects Growth in Tourist Traffic from Saudi Arabia, Oman and Bahrain over Visa Abolition
May 5, 2026
Sarajevo TimesSarajevo Times
Follow US
© 2012 Sarajevo Times. All Rights Reserved.
  • ABOUT US
  • IMPRESSUM
  • NEWSLETTER
  • CONTACT
Go to mobile version
adbanner
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?